    Bandaranaike International Airport VCBI/CMB is going to have an upgrade+Replacement for the Instrument Landing System (ILS). A new System will be installed within next few months.
    And, A new ILS will be installed at Ratmalana International Airport VCCC/RML to continue 24*7 All weather Operations within next few months.

    Leave a comment:


  • banuthev
    replied
    Originally posted by WizzWaveSien
    https://adaderana.lk/news/cmqby9j5g0008356qf39huzvi


    Excellent news guys, BIA T2 will be resuming construction soon in November, and Gov is actively working on renovating T1 and is preparing a masterplan for it.
    T2's completion in May 2029 is a long way off. Renovating T1 to modern standards is a sensible decision, as both the interior and exterior need to be updated.

    Leave a comment:


  • Haleef
    replied
    When is the new upgrades to the terminal 1 starting?

    Leave a comment:


  • suganya07
    replied
    Originally posted by WizzWaveSien
    Hey guys, Gov recently announced that they will be investing around RS. 15 billion (Around 45M USD) to renovate Terminal 1. Some pics are attached in the article below. Not sure about the timeframe, but expected to begin alongside T2's construction resumption.

    The Sri Lankan government has launched a Rs. 15 billion project to fully modernize Terminal 1 at Bandaranaike International Airport (BIA), Katunayake, without relying on foreign loans. The initiative aims to address growing passenger congestion and support the country’s expanding tourism sector.   Deputy Minister of Ports and Civil Aviation Janitha Ruwan Kodithuwakku stated that […]


    hey lads here are some of the new pictures. Do you think it is possible to do the renovation while the airport is operating?
    Attached Files

    Leave a comment:


  • WizzWaveSien
    replied
    Hey guys, Gov recently announced that they will be investing around RS. 15 billion (Around 45M USD) to renovate Terminal 1. Some pics are attached in the article below. Not sure about the timeframe, but expected to begin alongside T2's construction resumption.

    The Sri Lankan government has launched a Rs. 15 billion project to fully modernize Terminal 1 at Bandaranaike International Airport (BIA), Katunayake, without relying on foreign loans. The initiative aims to address growing passenger congestion and support the country’s expanding tourism sector.   Deputy Minister of Ports and Civil Aviation Janitha Ruwan Kodithuwakku stated that […]


    The Sri Lankan government has launched a Rs. 15 billion project to fully modernize Terminal 1 at Bandaranaike International Airport (BIA), Katunayake, without relying on foreign loans. The initiative aims to address growing passenger congestion and support the country’s expanding tourism sector.

    Deputy Minister of Ports and Civil Aviation Janitha Ruwan Kodithuwakku stated that the project will be funded entirely through local government resources while the construction of Terminal 2 continues. Planned upgrades include expanding the departure hall, improving security and immigration processing, redesigning the arrivals area and modernizing baggage handling systems.

    Leave a comment:


  • MAW2000
    replied
    Originally posted by Serendib

    Could they be upgrading the runway to 4,000m to support the increase in cargo aircraft? If I am not mistaken, extending the runway is only possible on the land side, correct?
    Increasing the Runway Length is quite hard from the Landside/Kimbulapitiya Road.

    Leave a comment:


  • Serendib
    replied
    Originally posted by WizzWaveSien
    https://economynext.com/no-second-ru...nister-275167/

    No second runway for BIA until 2055, instead government will be focusing on upgrading the existing runway to 4000m.
    Could they be upgrading the runway to 4,000m to support the increase in cargo aircraft? If I am not mistaken, extending the runway is only possible on the land side, correct?

    Leave a comment:


  • banuthev
    replied
    Does Katunayake really not need a second runway until 2055?

    Mr. Ruwan Kodithuwakku, Deputy Minister of Ports and Civil Aviation, recently announced that Katunayake Airport will not require a second runway until 2055, citing recommendations from an international master plan.

    ​For comparison, London Gatwick—one of the world’s busiest airports—handles more than 250,000 flight movements per year using primarily a single runway. However, due to current limitations and technical deficiencies at BIA (such as a lack of high-speed exit taxiways), it takes longer for aircraft to land and vacate the runway.

    ​Industry experts suggest that modernizing the existing infrastructure is a more practical solution than constructing a new runway.

    ​However, if Katunayake Airport is to truly become a developed, world-class international hub, what other improvements—beyond a runway upgrade—should be prioritized?

    Please share your thoughts in the comments.

    Leave a comment:


  • WizzWaveSien
    replied

    Construction work on the second passenger terminal at Bandaranaike International Airport (BIA) in Katunayake, which was halted due to the economic crisis, is scheduled to resume in November this year.


    Issuing a statement, the Ministry of Ports and Civil Aviation said it expects to complete the project within 30 months from the date of resumption.
    Excellent news guys, BIA T2 will be resuming construction soon in November, and Gov is actively working on renovating T1 and is preparing a masterplan for it.

    Leave a comment:


  • banuthev
    replied
    Originally posted by WizzWaveSien
    https://economynext.com/no-second-ru...nister-275167/

    No second runway for BIA until 2055, instead government will be focusing on upgrading the existing runway to 4000m.
    Interesting update. Does anyone know if the 4000m upgrade includes modernizing the taxiway layout or terminal capacity to match? A longer runway helps with heavy aircraft, but it won't solve congestion issues if the ground infrastructure stays as it is. Curious to see the official project scope for this.

    Leave a comment:


  • WizzWaveSien
    replied
    Sri Lanka’s main airport, the Bandaranaike International Airport (BIA) in Katunayake, will not see a second runway built until at least 2055 following recommendations from an international master plan, Deputy Minister of Ports and Civil Aviation Janitha Ruwan Kodithuwakku said.


    No second runway for BIA until 2055, instead government will be focusing on upgrading the existing runway to 4000m.

    Leave a comment:


  • Ven35K
    replied
    Originally posted by banuthev

    Is this true JAF runway expansion to complete by July this year?
    No update yet on the JAF runway upgrade, work on the runway expansion itself hasn’t started. The vegetation near the RWY23 side has been cleared/cropped. On the terminal side, Phase 1 is expected to be completed around July–August, though it’s not confirmed yet. As per officials, the target is still July. After that, the temporary terminal will be converted into the permanent structure under Phase 2. Most likely, the entire terminal will be ready by July next year.

    Leave a comment:


  • MAW2000
    replied
    Originally posted by banuthev

    Noticed there were few QR aircraft and GF A321neo stored at CMB due to middle east tensions. I wonder why these were not stored in HRI.
    As per my knowledge,
    Existing Landing and Parking permits, Reactivating aircrafts after long parking period, Ability to reposition aircrafts at homebase as a revenue flight instead operating a ferry flight.

    Leave a comment:


  • banuthev
    replied
    Originally posted by MAW2000

    Because HRI has very limited capabilities compared to Gulf carriers' requirements.
    Noticed there were few QR aircraft and GF A321neo stored at CMB due to middle east tensions. I wonder why these were not stored in HRI.

    Leave a comment:


  • MAW2000
    replied
    Originally posted by Serendib
    Top Gulf airlines have not responded to Sri Lanka’s invitation to use the Mattala Rajapaksa International Airport (MRIA), Deputy Civil Aviation Minister Janitha Ruwan Kodithuwakku said.
    Because HRI has very limited capabilities compared to Gulf carriers' requirements.